Simple process costing

For a single product made in bulk without stock, simply divide total cost by output.

Worked example

A waterworks (one product, no stock) had total costs of £148,280.00 for 4,000 m³ in the year. Work out the cost per m³ and the price with a 9% profit mark-up.

Worked solution

  1. 1.Simple process costing: cost per unit = £148,280.00 / 4,000 = £37.07
  2. 2.Price = £37.07 × 1.09 = £40.41

Typical mistake: Working out the mark-up on the price instead of on cost.

Your turn

Three problems of exactly this type, each time with new numbers. Amounts with or without thousands separators.

Task 1 of 3Process costing

Task

A waterworks (one product, no stock) had total costs of £1,491,270.00 for 33,000 m³ in the year. Work out the cost per m³ and the price with a 11% profit mark-up.

Cost per m³ in £

£

Price per m³ in £

£

Amounts like 12,500 or 12500.50; percentages as a number (12.5). Round to the penny or 2 decimal places.

Formulas for this topic
  • Simple: cost per unit = total cost / output
  • Two-stage: production cost / units made + admin and selling / units sold
  • Equivalence numbers: equivalent units = Σ output × factor; cost per unit = cost per equivalent unit × factor

Typical mistake: Working out the mark-up on the price instead of on cost.

Frequently asked questions

What is the typical mistake in "Simple process costing"?

Working out the mark-up on the price instead of on cost.

When is two-stage costing needed?

When units made and units sold differ, i.e. stock is built up or run down.